• AITANA
  • ESPADAN
  • IRTA
  • MARIOLA
  • ANETO
  • MULHACEN
  • VELETA

GENERAL PREPARATIONS

After thoroughly cleaning the subfloor, start laying from left to right. Position the
first plank so the tab is facing you. Placing the plank 6 mm / 1/4¨ from the left corner of the wall. Use
spacers between the wall and the floor.

TOOLS REQUIRED: Spacers, rubber mallet, ruler, pencil, tape measure, utility knife, tapping block, 0.15
mm moisture barrier, square, transition moldings, jamb saw, chalk line, eye protection, level, knee pads
(optional), broom or vacuum.

• Prior to installation, inspect the material in daylight for visible faults/damage, including defects
or discrepancies in color or shine; check the edges of the flooring for straightness and any damage. No claims
on surface defects will be accepted after installation.

• It is preferable to lay boards perpendicular to the window, following the direction of the main
source of light. For the best result, make sure to always work from 3 to 4 cartons at a time, mixing the planks
during the installation.

• Check if subfloor/site conditions comply with the specifications described in these instructions. If
the subfloor is not within specifications, DO NOT INSTALL, and contact your supplier.

• Flooring products can be damaged by rough handling before installation. Exercise care when handling
and transporting these products. Store, transport and handle the cartons in a manner to prevent any damage.
Store cartons flat, never on edge.

• Flooring products can be heavy and bulky. Always use proper lifting techniques when handling these
products. Whenever possible, make use of material-handling equipment such as dollies or material carts. Never
lift more than you can safely handle; get assistance.

• Calculate the room surface prior to installation and plan an extra 5-10% of flooring for cutting
allowance.

• The environment where the flooring is to be installed is critically important with regard to
successful installation and continued performance of the flooring products. The flooring is intended to be
installed in interior locations only. These interior locations must meet climatic and structural requirements as
well.

• In most cases, this product does not need to be acclimated. However, if the boxes of flooring were
exposed for over 2 hours to extreme temperatures under 10°C or over 35°C within 12 hours before the
installation, acclimation is required. In this case, keep the boards at room temperature for at least 12 hours
in an unopened package before you start the installation. The room temperature must be maintained consistently
between 20-25°C before and during the installation.

• The flooring should only be installed in temperature ranges between 20-25°C, it is necessary to
maintain a constant temperature before and during the installation. Portable heaters are not recommended as they
may not heat the room and subfloor sufficiently. Kerosene heaters should never be used.

• After installation, make sure that the flooring is not exposed to temperatures less than 10°C or
greater than 50°C.

• For floor surfaces exceeding 400 m2 and/or lengths exceeding 20 m, use expansion moldings.

 

SUBFLOOR INFORMATION

• The flooring can be installed over most existing hard surface floor coverings, provided that the
existing floor surface is structurally sound, clean, dry, and smooth. Subfloor variations should not exceed 5 mm
over 3 m.

• The substrate should not slope more than 25 mm per 2 m in any direction.

• Depressions, deep grooves, expansion joints, and other subfloor imperfections must be filled with
patching & leveling compound.

• Substrates must be free from excessive moisture or alkali. Remove dirt, paint, varnish, wax, oils,
solvents, and any foreign matter and contaminants.

• Do not use products containing petroleum, solvents, or citrus oils to prepare substrates as they can
cause staining and expansion of the new flooring.

• Although this floor is waterproof, it is not to be used as a moisture barrier.

• This product is also not to be installed in areas that have a risk of flooding such as saunas or
outdoor areas, seasonal porches, camping trailers, boats, RVs, lanais, rooms that are prone to flooding, or
rooms or homes that are not temperature-controlled.

• Existing sheet vinyl floors must not be cushioned and not exceed more than one layer in thickness.
Soft underlayment and soft substrates will diminish the product’s inherent strength in the clicking mechanism
and resisting indentations and could void the warranty.

• Acceptable job site conditions, including subfloor moisture conditions, must be maintained throughout
the lifetime of the flooring.

 

WOOD SUBFLOORS

• If this flooring is intended to be installed over an existing wood floor, it is recommended to repair
any loose boards or squeaks before you begin the installation.

• Wood subfloors must have no more than 12% MC (moisture content).

• Basements and crawl spaces must be dry. Use of a 0.15 mm poly-film is required to cover 100% of the
crawl space earth.

• We recommend laying the flooring crossways to the existing floorboards.

• All other subfloors – plywood, OSB, particleboard, chipboard, wafer board, etc. must be structurally
sound and must be installed following their manufacturer’s recommendations.

• DO NOT install over sleeper construction subfloors or wood subfloors applied directly over concrete.

 

CONCRETE SUBFLOORS

• Existing concrete subfloors must be fully cured, at least 60 days old, smooth, permanently dry,
clean, and free of all foreign material such as dust, wax, solvents, paint, grease, oils, and old adhesive
residue.

• The subfloor must be dry. With a pH limit of 9 and comply with moisture content requirements and
tested as per the below methods:

• Concrete moisture vapor emissions must not exceed 3.63 kg MVER (moisture vapor emission
rate) per 93 m2 per 24 hours. This can be measured with the calcium chloride test (ASTM F1869).

• 90% RH (ASTM F2170).

• Max. 2.5% moisture content (CM method / ASTM F2659).

• A minimum of 0.15 mm poly-film is required as a moisture barrier between the concrete subfloor and
the flooring.

NOTE: THE RESPONSIBILITY OF DETERMINING IF THE EXISTING FLOORING IS SUITABLE TO BE
INSTALLED OVER RESTS SOLELY WITH THE INSTALLER/FLOORING CONTRACTOR ON SITE. IF THERE IS ANY DOUBT AS TO
SUITABILITY, THE EXISTING FLOORING SHOULD BE REMOVED, OR AN ACCEPTABLE UNDERLAYMENT INSTALLED OVER IT.
INSTALLATIONS OVER EXISTING RESILIENT FLOORING MAY BE MORE SUSCEPTIBLE TO INDENTATION.

 

DO NOT INSTALL OVER

• Any type of carpet.

• Existing cushion-backed vinyl flooring.

• Floating floor of any type, loose lay, and perimeter fastened sheet vinyl.

• Hardwood flooring / wood subfloors that lay directly on concrete or over dimensional lumber or
plywood used over concrete.

 

IMPORTANT NOTICE

In-floor Radiant Heat: Flooring can be installed over 12 mm embedded radiant heat
using the floating method. Maximum operating temperature should never exceed 30°C. The use of an in-floor
temperature sensor is recommended to avoid overheating.

• Turn the heat off for 24 hours before, during, and 24 hours after installation when
installing over radiant heated subfloors.

• Before installing over newly constructed radiant heat systems, operate the system at
maximum capacity to force any residual moisture from the cementitious topping of the radiant heat system.

• Make sure that the temperature in the room is maintained consistently between
20-25°C before and during the installation.

• Once the installation is completed, the heating system should be turned on at the
ambient temperature and gradually increased in 5°C increments every 12 hours until reaching normal operating
conditions.

• Refer to the radiant heat system’s manufacturer recommendations for additional
guidance.

Warning: Electric heating mats that are not embedded into the
subfloor are not recommended for use underneath the floors. Using electric heating mats that are not
embedded and applied directly underneath the floors could void the warranty for your floor in case of
failure. It is best to install the flooring over embedded radiant floor heating systems and adhere to the
guidelines listed above.

Tip: The best idea to maximize the results of your heating system is
to have “ON” times with a comfortable temperature and “OFF” times with setback temperatures which are
normally 4°C lower than your comfort temperature. The setback temperatures are particularly important as
these won’t let the temperature of your room drop too much, meaning it is much quicker to heat your room
back to comfort levels when it’s needed.

 

INSTALLATION

• Remove trim molding, wall base, appliances, and furniture from the room. For the best results, door
jambs must be undercut to allow the flooring to move freely without being pinched. After preparation work, sweep
and vacuum the entire work area to remove all dust and debris.

• With a floating floor you must always ensure you leave a 6 mm gap between walls and fixtures such as
pillars, stairs, etc. These gaps will be covered with trim moldings after the floor is installed.

• Whenever possible, plan the layout so that the joints in the planks do not fall on top of joints or
seams in the existing substrate. The end joints of the planks should be staggered a minimum of 20 cm apart. Do
not install over the expansion joints. Avoid installing pieces shorter than 30 cm at the beginning or end of
rows.

• Do not install your kitchen cabinets directly over your floor. Built-in cabinets, kitchen cabinets,
islands, and similar heavy items must be installed first. Only then can the flooring be installed, leaving an
appropriate expansion gap around it. This gap will be covered with trim moldings after the floor is installed.
The quality of the floor can only be guaranteed if it is allowed to move freely. It must not be nailed, adhered,
or fastened to the subfloor in any way.

• Decide the installation direction. It is recommended to install the boards perpendicular to the
window following the direction of the main source of light.

• Measure the area to be installed: The board width of the last row shall not be less than 50 mm. If
so, adjust the width of the first row to be installed. In narrow hallways, it is recommended to install the
floor parallel to the length of the hall.

• UNDERLAY: If the floor DOES NOT HAVE a pre-attached underlayment, an additional underlayment is
recommended in order to improve acoustic performance and absorb some irregularities on the substrate. Best
results can be expected with an underlayment of 1 mm maximum thickness with a high density (>135 kg/m3), high
compressive strength (≥200 kPa according to EN 16354, ASTM D3575-20, Suffix D), and <10% thickness change
(according to ASTM D3575-20, Suffix B) that supports the click system during daily use. Thicker underlayments,
underlayments with a low density and inadequate compressive strength could damage the locking mechanism and will
void the warranty.

If the floor HAS a pre-attached underlayment, the use of an additional underlayment could damage the
locking mechanism and will VOID warranty.

IMPORTANT INSTALLATION INSTRUCTIONS

Important Information: Please read this before installation.

• Floor panels should be transported lying down. Floor panels should be stored in this position in
their unopened packaging in a dry place.

• Allow the floor panels to acclimatize (in their unopened packaging) to their environment for 48 hours
prior to installation. The ambient temperature should be at least 18°C (65°F) before and during installation.

• Inspect the floor panels before laying down. No claims will be entertained on materials that have
been used. Unused panels from opened packages should be resealed in their original packaging with tape.

• Floor panels must be laid as a floating floor system and must not be attached, in any way, to the
subfloor or any vertical structure. Ensure that adequate gaps of at least 5 mm from walls and any vertical
structures are maintained during installation. These gaps must be concealed with suitable skirtings or expansion
profiles after installation.

• Suitable expansion profiles should be used at the door threshold and if the floor length and width
exceed 12 m (40 ft) and 7 m (23 ft) respectively.

• It is recommended to use felt pads on furniture legs to avoid unintentional scratches on the floor.

 

INSTALLATION INSTRUCTIONS OF THE SPC PLANKS

Before you start

Do not store directly on concrete, allow air to circulate. Do not open cartons, spread them out and
protect the corners from damage.

Floor panels should be transported lying down. Floor panels should be stored in this position in their
unopened packages in a dry storage location.

Prior to installation, the planks/tiles should be acclimatized to the room conditions. For this
purpose, the original packages shall be stored horizontally unopened in groups of 4-5 for at least 48 hours in
the room with normal temperature conditions. Make sure that the temperature in the installation room is between
18°C and 25°C. The relative humidity should be between 40% and 65% (minimum and maximum values, respectively).
Both limit values must also be maintained during installation and later, in the course of regular use of the
dwelling. The subfloor temperature must be at least 15 °C. To avoid damage to the product, handle the packages
carefully and open them just before installation.

Slight variations in color and structure are designed to enhance the natural look. Mixing planks or
tiles during installation creates a more visual pattern. Avoid exposure to direct sunlight for extended periods
of time. Prolonged exposure to direct sunlight and temperature variations can affect the floor’s fastening
system and cause discoloration. Contact your flooring representative for additional information.

Inspect all planks or tiles for damage prior to installation. No claims will be accepted for flooring
that has been cut to size and/or installed.

Consideration should be given to load limits and high point loads so as not to prevent the floor from
floating.

 

THE SUBFLOOR

Proper subfloor preparation is an important part of a successful installation. Roughness or
irregularities in the subfloor can be transmitted through the new floor. All subfloors should be smooth and dust
free, with a flatness tolerance of no more than 3 mm (1/8”) over a distance of 3.05 m (10’). Cracks and holes
should be filled with quick-setting cement-based polymer or self-leveling compound.

Any unevenness greater than 3 mm should be sanded or leveled. The surface should be clean of dirt, oil,
glue residue, etc. Carpet staples or adhesive residue should be removed prior to installation. Gaps or
protrusions in the subfloor will prevent the planks from fitting properly.

Although VLOOK SPC planks or tiles are water resistant, they should not be used as a moisture barrier.
The subfloor must be completely dry before installing VLOOK SPC flooring. VLOOK SPC Flooring does not warrant
and is not responsible for damage to the subfloor due to moisture related problems.

On floors where vapour emissions are present, a 0.15mm poly-plastic blanket should be installed prior
to installing VLOOK SPC floors. All concrete floors should use plastic blankets for additional moisture
protection.

The subfloor must be clean, solid and flat in construction. Any protrusions caused by paint or plaster
drips, etc. must be removed.

VLOOK SPC click planks or tiles can be installed over existing firm flooring (linoleum, PVC), but the
textile flooring must be removed. When laying the flooring over tiles, fill the gaps with grout or patch to
ensure a smooth surface.

VLOOK SPC click tiles are already quiet when walked on. Additional noise reduction is only possible by
using specialized materials.

 

INSTALLATION

1. First row, first plank: After thoroughly cleaning the subfloor, you should begin laying from left to right. Position the first plank so that the grooved edge is facing you. Place the floorboard 6 mm from the left wall. Use spacers between the wall and the floorboard.

2. First row, second plank: Drop the plank and gently tap down the end with a rubber mallet so it firmly locks into the previous plank until both are at the same height. Make sure both planks are perfectly aligned. It is crucial that after the short edges of two connecting planks are correctly aligned and the rubber mallet contacts the plank in the area directly above the short edge, allowing for correct locking. Note: Tapping the area close to the short edge, but not directly above it, may result in permanent damage to the joint. Continue installing the first row until you reach the wall on the right.

 

IMPORTANT: If you notice both planks aren’t at the same height or are not well-locked together, please follow the disassembling instructions at the bottom of the page, disassemble, and check if any debris stuck inside the lock is obstructing. Failure to properly line up the end joint and attempting to force it in while out of alignment could result in permanent damage to the end joint.

 

3. First row, last plank: At the end of the first row, leave an expansion gap of 6 mm to the wall and measure the length of the last plank to fit.

4. To cut the plank: Use a simple utility knife and ruler, and with the top side facing up, score heavily and several times on the same axis. The knife will not go through the surface but make a deep cut. You can then snap one half of the plank using your other hand to hold down the second placing it very close to the cut. The plank will split naturally.

5. Second row, first plank: Start the second row with the leftover cut part of the last plank of the previous row. This small plank should measure at least 30 cm. Otherwise, cut a new plank in half and use it to begin the second row. The end joints of each adjoining row should not be closer than 20 cm to each other. Whenever practical, use the piece cut from the preceding row to start the next row.

6. Second row, second plank: Click the long side of the plank into the previous row and place it tight to the short end of the previous plank with an angle of 25-30°. Drop the plank and gently tap on the end with a rubber mallet so it firmly locks into the previous plank until both are at the same height. Make sure both planks are perfectly aligned.

7. After finishing the installation of every row: Use a tapping block and a small hammer or rubber mallet to gently tap the planks into the click of the previous row to make sure they are tightly clicked together and make sure there is no gap between the long side of the planks installed. Any gapping can compromise the whole installation.

8. Tip: After the first 2-3 rows of planks are installed, they should be checked with a string line to ensure that rows are still running straight. If they are not, it could be that the starting wall has some irregularities that caused bowing in the installation. If so, the starting row of planks may have to be scribed and re-trimmed to account for any unevenness in the wall. This can be done without having to disassemble the beginning rows.

9. To lay the last row: Position a loose board exactly on top of the last row laid. Place another board on top, with the tongue side touching the wall. Draw a line along the edge of this board, to mark the first board. Cut along the edge of this board to mark the first board. Cut along this line to obtain the required width. Insert this cut board against the wall. The last row should be at least 50 mm wide. The spacers can then be removed.

10. Holes for pipes: Measure the diameter of the pipe and drill a hole that is 12 mm larger. Saw off a piece as shown in the figure and lay the board in place on the floor. Then lay the sawed-off piece in place.

11. Door molding and skirting: Lay a board (with the decorative side down) next to the door molding and saw as shown in the figure. Then slide the floorboard under the molding.

 

INSTALLATION IN WET AREAS

IMPORTANT: This product is not warranted for installation in wet areas with running water and areas with built-in drains, e.g., pool or shower areas.

• Use a T-molding to separate the wet area from the rest of the installation.

• Fill the expansion spaces with a compressible PE foam backer rod and cover them with a flexible 100% silicone sealant around the entire perimeter of the installation before installing moldings.

Branded and generic silicone tubes are available at any local home center or hardware store. IMPORTANT: Do not use acrylic sealant.

• Apply silicone sealant to connections to doorframes or any other fixed objects.

 

FINISHING THE INSTALLATION

• Protect all exposed edges of the flooring by installing wall molding and/or transition strips. Allowing slight clearance between the molding and the planks. Make sure that no plank will be secured in any way to the subfloor.

• At doorways and at other areas where the flooring planks may meet other flooring surfaces, the use of a transition molding is required to cover the exposed edge but do not pinch the planks. Leave a 6 mm gap between the planks and the adjoining surface.

 

MAINTENANCE

• Use appropriate window coverings, such as drapes, window treatments, or UV-tinting on windows, to protect the product from direct sunlight as long-term exposure to direct sunlight can potentially lead to discoloration.

• Sweep or vacuum daily using soft bristle attachments. Do not use a vacuum equipped with a beater bar.

• Do not buff or sand the surface.

• Clean up spills and excessive liquids immediately.

• Damp mop as needed and use neutral cleaners recommended for vinyl flooring.

• The use of residential steam mops and spray mops on this product is allowed. Use at the lowest power with a suitable soft pad, and do not hold a steam mop on one spot for an extended period of time (longer than 30 seconds). Refer to the mop’s manufacturer instructions for proper usage.

• Use proper floor protection devices such as felt protectors under furniture. Equip wheeled-type office chairs and other rolling furniture with wide-surface, casters at least 5 cm in diameter.

• Place a walk-off mat at outside entrances to reduce the amount of dirt brought into your home. Do not use mats with latex or rubber backing since these backings can cause permanent discoloration.

• Do not use abrasive cleaners, bleach, or wax to maintain the floor.

• For stubborn spills use low odor mineral spirits or denatured alcohol applied to a clean cloth. Never pour chemicals directly on the floor.

• Do not drag or slide heavy objects across the floor.

• The flooring can be used in homes where wheelchairs are needed, but only certain thickness products can be installed for that purpose – not including pre-attached backing, at least 5 mm thick product. The flooring must not be applied to ramps. Motorized wheelchairs are NOT to be used.

 

DISASSEMBLING

Separate the whole row by lifting it up delicately at an angle. To separate the planks, leave them flat on the ground and slide them apart. If planks do not separate easily, you can slightly lift up the planks (5°) when sliding them apart.

 

1. Getting Started

Check the boards before starting to make sure they are not damaged in any way or have quality defects. Remember to clean the subfloor.

2. First row

Start the installation of the planks in the left corner, with the tongue side facing the wall. Be sure to place the short side of the plank 5 mm from the wall. The long side can be put in place when three rows have been assembled.

3. Next boards

Place the end section of the next board at an angle to the first and then lay it down. Complete the first row in the same manner.

4. Last board in a row

Lay the last board face down and the short side without the locking strip towards the wall. The distance to the wall should be at least 5 mm. Mark where the board is to be cut.

5. Cutting the boards

Place the board face down on the work surface and cut it to size with a circular saw. Use a fine-toothed type if using a handsaw. In this case, cut the boards face up.

6. Starting the second row

Use a piece cut from the previous row to start the next row. This should be at least 30 cm long. If this piece is too short, start with a new board cut in half. Always make sure that the end joints are staggered randomly by at least 30 cm.

7. Continue laying the floor.

Place the board at an angle against the board of the previous row, press forward and bend it down at the same time.

8. Continue laying the floor.

Place the short end of the angled board against the previously installed board and bend it down. Make sure the board is positioned on the integral locking strip of the board in the previous row.

9. Continue laying the floor.

Lift the board together with the board that was previously placed in the row by about 25 mm and press it against the previous row. Lower the panel again as soon as the boards are well positioned. Do not press the board all the way down. After all boards in the row are in place, press all boards against the subfloor before starting the next row.

10. Laying the last row.

To lay the last row, measure and cut the board. Allow 5 to 6.5 mm to the wall.

11. Holes for pipes

Measure the diameter of the pipe and drill a hole 10 mm larger. Cut a piece and set the board in place on the floor. Then install the cut out piece in place using carpenter’s glue.

12. Molding and door circumvention.

Place a board and any additional underlayment (decorative side down) next to the door molding and saw. Then slide the board under the molding.

13. Post-installation work.

Keep the floor clean and protected until the work is completed and the furniture is in place.

14. Underfloor heating.

VLOOK SPC floors can be installed with underfloor heating (only water underfloor heating is recommended) and with aerothermal systems. For optimal use, each room should not exceed 64m2.

15. Built-in sound insulation mantle.

VLOOK SPC floor coverings already have a built-in sound insulation mantle, so there is no need to add any additional sound insulation mantle on the floor.

 

CARE AND MAINTENANCE

Do not wax or polish your SPC click floor.

For daily cleaning, use a vacuum cleaner with a wand, a broom or a slightly damp mop.

Do not clean the floor with abrasive cleaners, abrasive scouring pads or powdered products.

It is recommended that suitable mats be placed at entrances to collect dirt, sand and pebbles.

Use only colourfast carpets on your floor. Do not place rubber or latex-backed mats or coconut fibre mats on the floor as they may discolour or damage the surface, which in turn may cause a magnifying glass effect affecting the dimensional stability of the parts, leading to warping and buckling.

Furniture that is moved frequently should be equipped with felt pads to avoid scratching the floor. Heavy furniture and appliances should be equipped with large-area, non-staining floor protectors. Use an office chair mat in areas where office chairs with casters are used.

Care should be taken whenever furniture is moved; furniture should never be dragged across the floor. If necessary, use suitable pads. Do not drag heavy furniture directly on the pavement. Always use a support base, such as a mat, even when using a wheeled trolley or when heavy objects have wheels.

Do not place heavy furniture on the flooring. Do not screw any decorative or protective elements to the flooring, this could create discontinuity in floating floors.

Avoid prolonged exposure to direct sunlight by installing curtains/blinds in the window area.

Maintain the temperature after installation between 5º and 35º and the humidity between 40% and 65%.

Keep pet nails trimmed. Like natural wood, SPC flooring can be scratched by untrimmed pet nails.

If underfloor heating is used (only water underfloor heating is recommended), the heating should not be switched on abruptly. The temperature should be raised gradually without the floor reaching 27°C.

 

TECHNICAL SPECIFICATIONS

Product type

Overall thickness

Wear layer

Finish

SPC (Rigid LVT)

5.0mm

0.55mm

Anti-microbial PureCoat UV coating

Anti-microbial UV coating

Installation

Bevel

Backing type and thickness

Floating (Tight lock)

Cut bevel on 4 sides

1mm IXPE

 

CLASS OF USE AND WARRANTY

Domestic

Domestic Warranty

23 Heavy

Lifetime Limited

Commercial

Commercial Warranty

31 Moderate

33 Heavy

15 Years Limited

 

ENVIRONMENTAL IMPACT

Life Cycle Assesment

Oct 2022

Environmental Product Declaration

Oct 2022 – Oct 2027

 

CERTIFICATIONS

CE Marking

UKCA Marking

IAC Gold

Compliant

Compliant

Compliant

GreenGuard Gold

Assure

Product Health Declaration

Compliant

Compliant

Compliant

 

CHEMICAL PROPERTIES

 

Norm: EN 14041

Item Test Method Requirement Result
Emissions EN 717-1 ≤0.12mg/m3 Compliant

 

Norm: Decret No.2011-321

Item Test Method Requirement Result
Emissions ISO 16000 VOC A+ (TVOC <1000µg/m3) Compliant

 

Norm: CDPH

Item Test Method Requirement Result
Emissions Spectrometry, chromatography TVOC ≤220µg/m3 Compliant

 

Norm: CPSIA & Prop 65

Item Test Method Requirement Result
Ortho-Phthalates CPSC-CH-C-1001-09.4 N.D. Compliant

 

Norm: REACH

Item Test Method Requirement Result
SVHC Spectrometry, chromatography ≤0.1% Compliant

 

PHYSICAL PROPERTIES

 

Norm: ISO 10582

Item Test Method Requirement Result
Length ISO 24342 ≤0.15% of nominal length up to max 0.5mm Compliant
Width ISO 24342 ≤0.1% of nominal width up to max 0.5mm Compliant
Squareness and straightness ISO 24342 ≤0.25mm/≤400mm, ≤0.35mm/≤400mm Compliant
Total thickness (with backing) ISO 24346 +0.13mm/-0.1mm, max ±0.15mm Compliant
Wear layer thickness ISO 24340 +13%, -10% Compliant
Dimensional stability (6hrs at 80°C) ISO 23999 ΔW/ΔL ≤0.15% Compliant
Curling ISO 23999 ≤1mm Compliant
Castor chair ISO 4918 Moderate Commercial 15,000R Heavy Commercial 25,000R Compliant
Residual indentation ISO 24343-1 ≤0.1mm Compliant
Light fatness (blue wool) ISO 105-B02:2014 Method 3A ≥Grade 6 Compliant
Flatness ISO 10582 Appendix B Length: ≤0.50% (concave) / ≤1.0% (convex),
Width: ≤0.10%(concave) / ≤0.15% (convex)
Compliant
Openings ISO 10582 Appendix C Average ≤0.15mm / Max ≤0.2mm Compliant
Height difference ISO 10582 Appendix C Average ≤0.1mm / Max ≤0.15mm Compliant
Locking strength ISO 10582 Appendix D ≥1.5 KN/m Compliant

 

Norm: EN 16511

Item Test Method Requirement Result
Wear resistance EN 13329 /ISO 24338 Procedure A ≥4000 cycles (AC4) Compliant
Impact resistance EN 13329 Annex F ≥1600mm Compliant
Martindale (gloss retention) EN 16094 ≤MSR-A2 Compliant
Martindale (micro-scratch) EN 16094 ≤MSR-B2 Compliant
Furniture leg EN ISO 16581 No visible damage Compliant
Resistance to staining EN 438-2 Group 1 and 2: Grade 5
Group 3: Grade 4
Compliant
Swelling ISO 24336 ≤12% Compliant

 

Norm: EN 14041

Item Test Method Requirement Result
Thermal Resistance (R) EN 12664/ASTM C518 NA Compliant
Slipperiness EN 13893 ≥0.3 Compliant
Reaction to fire EN 13501-1 Class Bfl -s1 Compliant

 

Others

Item Test Method Requirement Result
Slipperiness DIN 51130 /DIN EN 16165 Annex B ≥R9 Compliant
Airborne sound transmission ISO 10140-2 N/A 67dB*
Impact sound transmission ISO 10140-3 N/A 42dB*
Impact sound transmission – Reduction ISO 10140-1 N/A 18dB* 20dB*

 

LEED SCORECARD

How our products fit into LEED v4

 

Credit Type:

LEED BD+C and ID+C EQ Credit: Low-Emitting Materials

Points:

1-3 points

Criteria:

Option 1. Product has been tested according to California Department of Public Health (CDPH) Standard
Method v1.2–2017 and complies with the VOC limits in Table 4-1 of the method. Additionally, the range of total
VOCs
after 14 days (336 hours) was measured as specified in the CDPH Standard Method v1.2 and is reported (TVOC
ranges:
0.5 mg/m3 or less, between 0.5 and 5 mg/m3, or 5 mg/m3 or more).

Option 2. Product has been tested according to EN 16516:2017 and complies with the LCI values from Table 1 of the
German
AgBB Testing and Evaluation Scheme (2015) and a formaldehyde limit of 10 micrograms per cubic meter. Additionally,
the
range of total VOCs after 28 days was measured as specified in EN 16516 and reported (TVOC ranges: 0.5 mg/m3 or
less,
between 0.5 and 5 mg/m3, or 5 mg/m3 or more)

Product Contribution:

CFL Rigid Core products are GreenGuard Gold and/or FloorScore certified (option1).

CFL Rigid Core products are IAC Gold certiifed, including compliance with German AgBB testing (option2).

 

Credit Type:

MR Credit: Building Product Disclosure and Optimization – Environmental Product Declarations

Points:

1 point

Criteria:

Option 1. Environmental Product Declaration (EPD) Environmental Product Declarations which conform to
ISO
14025 and EN 15804 or ISO 21930 and have at least a cradle to gate scope. Product-specific Type III EPD —
Products
with third-party certification (Type III), including external verification and external critical review are
valued
as 1.5 products for the purposes of credit achievement calculation.

Product Contribution:

CFL SPC (Made in China) LCA – Oct 2022;

CFL SPC (Made in China) EPD – Oct 2022 – Oct 2027.

 

Credit Type:

MR Credit: Building Product Disclosure and Optimization – Material Ingredients

Points:

1 point

Criteria:

Option 1. Material Ingredient Reporting Health Product Declaration. The end use product has a published
and
complete Health Product Declaration with full disclosure of known hazards in compliance with the Health Product
Declaration open Standard.

Option 2: Material Ingredient Optimization International Alternative Compliance Path – REACH Optimization (value at
100%
of cost or 1 product). End use products and materials have fully inventoried chemical ingredients to 100 ppm and
assess
each substance against the Authorization List – Annex XIV, the Restriction list – Annex XVII and the SVHC candidate
list, (the version in effect June 2013,) proving that no such substance is included in the product. If the product
contains no ingredients listed on the REACH Authorization, Restriction, and Candidate list.

Product Contribution:

CFL SPC (Made in China) Health Product Declaration – HealthRate Platinum (by GreenTag).

CFL products are REACH compliant.

 

WELL SCORECARD

The WELL Building Standard is founded on the understanding that facets of our environment interact with
personal, genetic and behavioral factors to shape our overall health and well-being. By compiling leading
practices
in building design and management and referencing existing standards and best practice guidelines set by
governmental and professional organizations, WELL works to harmonize and clarify existing thresholds and
requirements.

 

Facet: AIR

Feature:

Air quality standards

Part:

Standards For Volatile Substances

Requeriments:

The following conditions are met:
a. Formaldehyde levels less than 27ppb (0.027ppm)
b. Total volatile organic compounds less than 500ug/m3 (0.5mg/m3)

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

a. Formaldehyde emission are less than 0.05mg/m3.
b. The total volatile organic compounds are less than 0.5mg/m3.

 

Feature:

VOC Reduction

Part:

Interior Paints and Coatings

Requeriments:

The VOC limits of newly applied paints and coating meet one of the following requirements:
a. 100% of installed products meet California Air Resources Board (CARB) 2007, Suggested Control Measure (SCM)
for
Architectural Coatings, or South Coast Air Quality Management District (SCAQMD) Rule 1113, effective June 3,
2011
for VOC content.
b. At minimum 90%, by volume, meet the California Department of Public Health (CDPH) Standard Method v1.1-2010
for
VOC emissions

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

a. The VOC limits for California Air Resources Board (CARB) are less than 0.11ppm.
b. Measured Concentration of Total Volatile Organic Compounds (TVOC): Less than/equal to 0.5 mg/m3 (in
compliance
with CDPH/EHLB Standard Method v1.1 2010).
The product is GreenGuard Gold certified

 

Feature:

VOC Reduction

Part:

Flooring

Requeriments:

The VOC emissions of all newly installed flooring must meet all limits set by the following, as
applicable:
a. California Department of Public Health (CDPH) Standard Method v1.1-2010.

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

Conforms to the CDPH/EHLB Standard Method v1.1-2010 (California Section 01350), effective January 1,
2012,
for the school classroom and private office parameters when modeled as Flooring.
The product is GreenGuard Gold certified

 

Feature:

Fundamental Material Safety

Part:

Asbestos and Lead Restriction

Requeriments:

All newly-installed building materials meet the following materials composition requirements:
a. No asbestos.
b. Not more than 100 ppm (by weight) added lead.

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

a. No asbestos
b. The product contain less than 100 ppm

 

Feature:

Fundamental Material Safety

Part:

Lead Abatement

Requeriments:

For repair, renovation or painting on buildings constructed prior to any applicable laws banning or
restricting lead paint, lead evaluation and abatement.

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

The product contain less than 90 ppm

 

Feature:

Fundamental Material Safety

Part:

Asbestos Abatement

Requeriments:

To reduce hazards in buildings constructed prior to any applicable laws banning or restricting
asbestos,
the following testing, evaluation and abatement.

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

The product contain less than 90 ppm.

 

Feature:

Toxic Material Reduction

Part:

Flame Retardant Limitation

Requeriments:

Halogenated flame retardants are limited in the following components to 0.01% (100 ppm) to the extent
allowable by local code:
a. Window and waterproofing membranes, door and window frames and siding.
b. Flooring, ceiling tiles and wall coverings.
c. Piping and electrical cables, conduits and junction boxes.
d. Sound and thermal insulation.
e. Upholstered furniture and furnishings, textiles and fabrics.

Concept score:

OPTIMIZATION

How our product contribute to obtain WELL level certification:

The product don’t contain halogenated flame retardants

 

Feature:

Toxic Material Reduction

Part:

Phthalate (Plasticizers) Limitation

Requeriments:

DEHP, DBP, BBP, DINP, DIDP or DNOP (often found in polyvinyl chloride [PVC]) are limited in the
following
components to 0.01% (100 ppm):
a. Flooring, including resilient and hard surface flooring and carpet.
b. Wall coverings, window blinds and shades, shower curtains, furniture and upholstery.
c. Plumbing pipes and moisture barriers.

Concept score:

OPTIMIZATION

How our product contribute to obtain WELL level certification:

In accordance with US Consumer Product Safety Improvement Act 2008 (CPSIA) (H.R.4040) Title I, Section
108
& California Proposition 65 & Annex XV II item 51&52 of the REACH Regulation (EC) No. 1907/2006 and
amendment No. 552/2009, the product contains less than 100ppm.

 

Feature:

Toxic Material Reduction

Part:

Urea-Formaldehyde Restriction

Requeriments:

Urea-formaldehyde presence is limited in the following components to 100 ppm:
a. Furniture or any composite wood products.
b. Laminating adhesives and resins.
c. Thermal insulation.

Concept score:

OPTIMIZATION

How our product contribute to obtain WELL level certification:

The product contains urea formaldehyde less than 100ppm.

 

Facet: COMFORT

Feature:

Exterior Noise Intrusion

Part:

Sound Pressure Level

Requeriments:

Each regularly occupied space meets the following sound pressure level as mesured when the space and
adjacent spaces are unoccupied, but within 1 hour of normal business hours:
a. Average sound pressure level from outside noise intrusion does not exceed 50 dBA.

Concept score:

PRECONDITION

How our product contribute to obtain WELL level certification:

1. The product has Lnw = 42dB according to the standard ISO 10140-3
2. The product has Rw = 67dB according to the standard ISO 10140-2

 

Feature:

Internally Generated Noise

Part:

Sound Masking Limits

Requeriments:

If sound masking systems are used, sound levels fall within the following range, when measured from the
nearest workspace:
a. Open workspaces: 45 – 48 dBA.
b. Enclosed offices: 40 – 42 dBA

Concept score:

OPTIMIZATION

How our product contribute to obtain WELL level certification:

1. The product has Lnw = 42dB according to the standard ISO 10140-3
2. The product has Rw = 67dB according to the standard ISO 10140-2

 

Analised Characteristic Standard Units Result
Dimensions ISO 24337:2006 mm x mm 230 x 1235
Thickness EN ISO 24346 mm 5 mm
Thickness tolerance of wear layer EN ISO 24340 mm +13%, -10%
Wear resistance IP 0,5 EN 13329:Annex E Class Class 33 / Clase 33 Tráfico comercial intenso
Formaldehyde Emission EN 12149:1997 Test C mg/m³ Not detected
Vinyl Chloride Monomer EN 12149:1997 Test B mg/kg Not detected
Soluble cadmium EN 71-3:1994+AC:2002 mg/m³ Not detected
DEHP+BBP+DBP EN 14372 Not detected
DNOP+DIDP+DINP EN 14372 Not detected
Slip resistance DIN 51130:2014 Group ≥ R10
Testing of fire resistance EN 13501-1 Class B1 (B-s1, t0)
Thermal resistance EN 12667 m²K/W 0.04-0.05 m²K/W
Static electrical propensity EN 1815 kV ≤ 2.0 kV
Residual indentation ISO 24343-1:2012 mm ≤ 0.1 mm
Peeling strength ISO 24345 mm ≥ 70 N/50mm
Click tension force ISO 24334 kN/m ≥ 3 kN/m
Resistance to staining EN 26987 No contamination or corrosion
Curling after exposure to heat ISO 23999 mm ≤ 1 mm
Impact sound transmission – Reduction ISO 10140-1 dB 18dB 20dB

 

1. SCOPE OF APPLICATION

This Commercial Use Limited Warranty is offered by us and is Worldwide applicable. This warranty applies to our rigid core vinyl and thermoplastic flooring, purchased from authorized dealer and installed and used in commercial area. Commercial area is defined as: use in environments (which do not experience heavy commercial traffic) such as those outlined in the application table below. Applications considered “industrial” do not qualify for warranty coverage.

 

Examples of Business Type Commercial Use Recommended Application
Med clinic, retirement centers, Doctor’s offices, hospice, assisted living. All non-required “clean room” areas – Corridors, patient rooms, lobby, waiting rooms, cafeteria, exam rooms, common areas.
Professional offices (i.e. accountants, lawyers, etc.), banks. Offices, hallways, lobby, reception areas, break rooms, conference rooms.
Boutiques, retail store, art galleries, book-stores, coffee shops, gift shops, jewelry stores, beauty salons, barber shops. Dressing rooms, entire store.
Apartments, condos, military housing. Any room in these segments will be suitable, including common areas excluding bathrooms.
Hotel, motel, restaurants. Guest rooms, lobby, hallways, elevator.
Day-care, school, universities, libraries. Dorms, common areas, cafeterias, class rooms, auditoriums, libraries (excluding gymnasiums).

 

2. WARRANTIES

2.1. WEAR WARRANTY

We warrant to the original purchaser that the wear layer on our flooring:

• Will not wear through the decorative surface. Scratches, indentation or reduction in gloss level is not considered wear.

• Will not stain from normal household consumable items such as food or drink.

• Will not stain from pet (domestic cat or dog) stains, including urine, feces and vomit, providing it is immediately cleaned upon discovery. Stain resistance means the ability of the floor to resist (i.e. minimize or withstand) permanent stains for the warranty period.

• Will not fade as a result of direct sunlight or household lighting.

• Will be resistant to damage from normal household spills.

• In its original manufactured conditions, will be free from manufacturing defects. Starting from the date of purchase, but only if no exclusions are applicable and only if all conditions are fulfilled.

2.2. STRUCTURAL WARRANTY

We warrant the original purchaser that our flooring:

• Will not delaminate.

• In its original manufactured condition, will be free from manufacturing defects.

Starting from the date of purchase, but only if no exclusions are applicable and only if all conditions are fulfilled.

2.3. INSTALLATION OVER A RADIANT-HEATED SUBFLOOR WARRANTY

We warrant to the original purchaser starting from the date of purchase, the floor can be installed over an embedded radiant-heated subfloor, but only if no exclusions are applicable and only if all conditions are fulfilled:

• In-floor Radiant Heat: flooring can be installed over 1/2” / 12 mm embedded radiant heat using the floating method.

• Electric heating mats that are not embedded into the subfloor are not recommended for use underneath the flooring. Using electric heating mats that are not embedded and applied directly underneath the flooring could void the warranty in case of failure.

• The radiant heating system must incorporate electronic temperature controls.

• Heat must be off for 24 hours before, during and 24 hours after installation when installing over radiant heated subfloors.

• Before installing over newly constructed radiant heat systems, operate the system at maximum capacity to force any residual moisture from the cementitious topping of the radiant heat system.

• Concrete moisture vapor emissions should not exceed 8 lb / 3.63 kg (ASTM F1869) / 90 % RH (ASTM F2170) with a PH limit of 9 / max 2.5 % moisture content (CM method).

• Please respect the temperature range in the room before and during the installation as specified in the installation manual, or your warranty will be void.

• Once the installation has been completed, the heating system should be turned on and increased gradually (5-degree increments) until returning to normal operating conditions.

• Floor temperature must not exceed 85°F / 30°C. • Refer to the radiant heat system’s manufacturer recommendations for additional guidance.

2.4. MOISTURE WARRANTY

We warrant that all vinyl flooring and thermoplastic composite flooring in its original manufactured state to the original purchaser from the date of purchase, under normal and reasonable use, and the surface, when properly installed, shall be resistant to damage from mopping or normal household spills. This means planks or tiles will not swell, buckle or lose integrity. The moisture warranty does not cover flooding, leaking pipes, household mechanical failures, appliance leaks. Any damage to the subfloor and/or surrounding structure that is caused by standing water or flooding is not covered by this warranty.

2.5. PET WARRANTY

We warrant that the floor will resist staining caused by pet (domestic cat or dog) stains, including urine, feces, and vomit. Stain resistance means the ability of your floor to resist (i.e., minimize or withstand) permanent stains for the warranty period. However, accidents should be cleaned up immediately (within 24 hours), as the longer they sit, the more difficult they will be to remove. Any damage to the subfloor and/or surrounding structure caused by pets is not covered by this warranty.

3. EXCLUSIONS AND CONDITIONS

3.1. GENERAL EXCLUSIONS AND CONDITIONS

• Damage arising by not following relevant installation, care, maintenance and use instructions of the present warranty and the installation instructions provided.

• Damage arising from improper installation (for example installation on an unlevelled subfloor and installation when there is not sufficient perimeter expansion zone), improper care, improper maintenance or improper use.

• Damage caused by the use of underlayment for flooring with a pre-attached pad or using improper underlayment for flooring without a pre-attached pad.

• Damage arising because the flooring is exposed to extreme cold or extreme heat as specified in the provided installation manual.

• Damage caused by exposure to excessive moisture (for example excessive moisture in a concrete slab, excessive moisture from hydrostatic pressure, flooding, standing water, water underneath the flooring, excessive moisture as the result of malfunctioning appliances such as dishwashers, ice makers, refrigerators, sinks, pipes).

• Damage caused by spills which are not removed promptly.

• Normal wear and tear of the flooring.

• Normal changes in colour, gloss, grain pattern and tone (this is normal for flooring as it ages).

• Damage arising because the flooring is installed in an outdoor area, a solarium, a porch, a garage or areas similar to all of these.

• Damage arising because the flooring is not used under normal conditions.

• Damage arising from accidents, abuse, misuse, or the use of strong chemicals.

• Damage caused by an act of God (for example a natural disaster).

• Damage caused by vacuum cleaner beater bars or hard plastics, or metal caster wheels.

• Differences in aspect, colour, gloss, grain pattern and tone with the reference flooring sample in for example the store or showroom.

• Flooring that has been damaged or neglected during transportation.

• Scratches, marks, stains and other damage caused by exposure to “abrasives” such as pebbles, grit, sand, high heeled shoes, furniture, etc.

• Indentations.

• Damage to click joints or indentation due to heavy rolling loads.

• Damage of planks coming apart at the seams because they have been engaged/disengaged more than three times.

• Damage caused by the collections of dirt and moisture at entrances do due the lack of interior and exterior doormats.

• Damage caused by shoes having heeltaps or sharp objects protruding from the sole such as rocks, exposed nails and gravel.

• Damage caused by walking on with spike-or stiletto-heeled shoes.

• Damage caused by sliding or rolling heavy objects on the floor. A solid protective covering must be laid (must use at least 1/4” / 6 mm hard board) on your floor and gently “walk” the item a cross it. Carpet or cardboard is not adequate to prevent surface indentation or roller marks from occurring or scratches to the floor.

• Damage caused by non-compliant casters on furniture. Barrel-type caster wheels or wide, flat glides are best for protecting the floor. For areas with rolling chairs (e.g. desk area), ensure a protective mat is used under the chair.

• Damage caused by hard narrow furniture rollers. They must be replaced with wide rubber rollers.

This warranty is valid only to the original purchaser. It is not transferable and only applicable to the first installation of the flooring. The affected area must be visible and cover an area bigger than 0.038 inch2 / 25 mm2. This warranty does not apply to any products designated as B grade, cabin grades, closeouts, seconds, factory special, non-standard items and flooring sold “as is”.

It is the responsibility of the purchaser and the installer, whether they are professionals or a do-it-yourselves, to inspect all flooring and flooring accessories before installation. If during inspection the purchaser or the installer knows/discovers or can reasonably be supposed to know/discover (for example when the default is visible), that the flooring has a visible manufacturing issue, do not install the flooring. Please immediately contact the retailer from which the flooring was purchased. No claims will be accepted for flooring of which the purchaser or installer knew/discovered or can reasonably be supposed to have known/discovered, that there was something wrong with it. In such case we only warrant the part of the flooring which has not been installed yet.

We do not allow or authorize any other person or entity to alter the obligations and limitations in this warranty. This warranty is the complete and exclusive expression of our warranty and is in lieu of all other express and/or statutory warranties. Any implied warranties, including but not limited to the implied warranties, merchantability and fitness for a particular purpose are limited to this express warranty. However, some jurisdictions do not allow exclusion or limitation on how an implied warranty lasts, so the above limitation or exclusion may not apply to you.

We expressly exclude and will not pay consequential or incidental damages under this warranty. By this we mean for example loss, expense, inconvenience or damages, other than to the flooring itself, that may result from a defect in the flooring. However, some jurisdictions do not allow exclusion or limitation of incidental or consequential damages, so the above limitation or exclusion may not apply to you. We reserve the right to inspect the flooring and to remove samples for additional evaluation, if we consider this necessary. Any attempt to repair or replace the flooring without our consent will void this warranty.

The failure of either party to enforce any of the provisions of this warranty agreement shall not be construed as a waiver of such provision or a waiver of the right of any party thereafter to enforce each and every provision. This warranty gives you specific legal rights and you may also have other rights which vary from jurisdiction to jurisdiction. We will always respect these other rights. No implied warranties extend beyond the term of this written warranty.

4. WHAT YOU SHOULD DO IF ANY OF THE ABOVE LISTED PROBLEMS OCCUR

You should notify the original dealer of the defect within 30 calendar days after you know/discover the defect and within the validity period of this warranty. Your dealer can answer your questions and, if necessary, start to process a claim. If your notification takes place outside this period, our warranty will not be applicable. In order to enjoy the warranty, you are obligated to present:

• A valid proof of purchase in the form of the sales receipt for the flooring and other accessories related to the installation which may affect the installation quality such as but not limited to adhesive, moulding, underlay, moisture barrier, moulding, etc.

• A detailed description of the defect and/or a photograph or sample of the flooring that clearly shows the defect. Provide additional information requested by the factory to understand the root cause of the issue.

5. WHAT WE WILL DO If

we honour a claim under this warranty, we will – at our sole discretion – repair or refinish the defective material or we will refund the price of the flooring. If the flooring was originally installed by a certified professional installer and if there is a justified claim within the first 36 months from the date of the original purchase, we will also pay the reasonable labour costs to perform the repair or replacement.

This repair or replacement or refund will be a pro-rated percentage cost of the flooring and labour cost. This percentage is determined by the number of years remaining on the warranty and the length of the warranty. For example, if the claim is made 3 years after purchase on flooring warranted for 15 years, then 80% (12/15th) of the flooring cost will be considered.

This warranty is limited to the designs, colours, structures and styles available at the time of repair or replacement. If the original is no longer available, we have the right to substitute another design, colour, structure and style that is similar to the original and that has a similar value. We will always try to take into account the wish of the customer.